A. Preparation work

1. Construction tools

Pressure pad (quartz sand and convenient bags, bricks and other materials, as much as you can), art knives, adhesive tape, glue, turf, power line, hot air blower, bom line box, ruler and other small devices.

 

2. Personnel Composition

Unwinding: 2 people; holding the pad: 2 people; filling sandbags: 1 people; alignment: 1 people; adhesive: 1-2.

3. Preparatory work before construction

--Check whether the site meet the requirement.

--Check the field planess

--Check whether there are sundry, debris, gravel, etc. on site

--Put the roll of shock pad to the right position

--To line (Designated the first horizontal line which must be straight)

B. Construction steps

-Uniform marking on one side of the roll of the shock pad.
--Put the shock pad in order on the site.
--Draw a reference line on the field according to the release line of the shock pad.
--According to the site designed map, first place the top edge of the roll. After unwinding, the edge line of the shock pad must be kept in a straight line. Both ends of the roll of the shock pad should be left at a length of 30 cm and pressed immediately after adjustment.
--Spread the second roll next to the first roll. The roll  can be paved quickly and can be adjusted when rolling or after spreading. The position cannot by adjusted by pulling the shock pad. It can be adjusted by method of single-direction translation. In general, two people are needed to adjust the position to prevent damage or wrinkle the mat;
--Adjust the position. Leave no gap between the roll and the roll and make them be tight (can't be pulled, keep the single direction translation). Adjust the position and press the mat with heavy objects to facilitate the next step.
--According to the mark of each roll, spread the following roll of shock pad along the adjacent roll.  Fine-tuning the position with gaps by single direction translation. Then press the mat with heavy objects to prevent displacement due to uncertain factors.
--Welding with a special hot air gun. No more pulling during welding.  It is recommended to carry out the construction at temperatures below 30 degrees.
--When installing  six rolls of shock mat for the first time, spread two rolls of lawn on the mat. The mat and the lawn were alternately arranged. Then, after each three rolls of mat is laid, a roll of lawn is spread on the mat in order.
--Do not touch the mat when bonding the lawn; it is recommended to scribe on the lawn.  Please pay attention to the strength when implanting the white line so as to prevent the mat from being cut.
--After the lawn is bonded, remove the excess mat material on both sides and glue the mat to the ground.
--Any damaged parts of the mat can be cut out neatly and replaced with spare materials and tape.
--Since the material is relatively light, the temperature difference between the morning and the night will form ground steam, which will easily cause the shock mat to rise and form an uneven phenomenon. This is a normal phenomenon. It will not appear after the lawn is filled with sand.
 

 